Referendum Project Updates

Your park district 2026
In March 2024, the majority of Lemont residents voted in favor of a referendum for park district updates and development without raising taxes for Park District debt service. With this referendum, we outlined four projects including the development of Derby Farms Park, Centennial Community Center expansion & renovations, the CORE Fitness & Aquatic Complex enhancements, and new pickleball and tennis courts on 127th Street.
Progress Reports as of June 2026
Centennial Community Center:Â Construction has begun on the North and South corridors. The facility is still open, as well as the Outdoor Pool. Please use the main entrance of the building to access both the community center and the outdoor pool.
The CORE Fitness & Aquatic Complex:Â Construction has begun on the East side of the CORE. Impacted fitness classes have been relocated-please see fitness class schedule for changes.
Tennis Facility on 127th Street: Staff are finalizing civil engineering plans with architects and engineers. Â Tree preservation measures have begun, with construction to begin in the coming weeks.
Derby Farms Park:Â Staff are finalizing plans with the architects and engineers for this park. The team is collaborating with multiple agencies permitting with the Village of Lemont, Metropolitan Water Reclamation District, and Cook County Highway Department. A traffic signal has been approved for installation at 131st & Derby Roads to assist in traffic calming.Â
**Please note, all photos are architectural renderings. These may change based on budgets and bids. Figures represented are construction cost.Â
Centennial Community Center Renovation Â
Anticipated Completion Date
2026-2028
Projected Estimated Budget $6.9MÂ Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â
Project Summary
- New gathering spaces
- Expansion, including large programming & event space with kitchen
- New programming rooms
- Enhanced lobby
- Infrastructure enhancements
- Improved accessibility
The CORE Fitness & Aquatic Complex Â
Anticipated Completion Date
2026-2028
Projected Estimated Budget $2.0M
Project Summary
- Additional fitness studios
- Enhanced lobby
- Increased programming space
Tennis & Pickleball on 127th St Anticipated Completion Date
2026-2027
Projected Estimated Budget $2.5M
Project Summary
- Six pickleball courts at Centennial Park
- Tennis facility with four courts
- Additional parking
- Open space
Derby Farms Park (131st & Derby Rd) Anticipated Completion Date
2026-2027
Projected Estimated Budget $4.6M
Project Summary
- Splash pad
- Multi-sport fields
- Shelter & concession stand
- Walking & fitness path
- Playground
- Restrooms
- Parking